Use the following information and the attached editable MRP tableau worksheet to determine a complete material requirements plan for the 5 week planning horizon. A garden equipment manufacturer has a product that it makes which is represented by the following product structure tree along with other pertinent data:
ABC-51
————————————————————————–
l l l
l l l
W X (3 L
l l
l ———————————-
P (4 l l
l l
P R (2
Inventory Records File
|
Item |
Lead Time |
On Hand |
Lot Size |
Safety Stock |
Sched. Receipt |
|
ABC-51 |
1 |
15 |
L4L |
0 |
— |
|
L |
1 |
12 |
L4L |
0 |
— |
|
P |
1 |
53 |
100 |
10 |
140 in wk 1 |
|
R |
1 |
30 |
L4L |
10 |
28 wk 1 |
|
W |
1 |
10 |
20 |
0 |
— |
|
X |
2 |
25 |
40 |
0 |
— |
Master Production Schedule (Weeks)
Product 1 2 3 4 5
ABC-51 0 0 50 0 75
|
Horizon Period |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
Item: |
Lot Size: |
LT: |
SS: |
||||||
|
Gross Requirements |
|
|
|
|
|
|
|
|
|
|
Scheduled Receipts |
|
|
|
|
|
|
|
|
|
|
Projected On Hand |
|
|
|
|
|
|
|
|
|
|
Net Requirements |
|
|
|
|
|
|
|
|
|
|
Planned-Order Receipts |
|
|
|
|
|
|
|
|
|
|
Planned-Order Releases |
|
|
|
|
|
|
|
|
|
|
Item: |
Lot Size: |
LT: |
SS: |
||||||
|
Gross Requirements |
|
|
|
|
|
|
|
|
|
|
Scheduled Receipts |
|
|
|
|
|
|
|
|
|
|
Projected On Hand |
|
|
|
|
|
|
|
|
|
|
Net Requirements |
|
|
|
|
|
|
|
|
|
|
Planned-Order Receipts |
|
|
|
|
|
|
|
|
|
|
Planned-Order Releases |
|
|
|
|
|
|
|
|
|
|
Item: |
Lot Size: |
LT: |
SS: |
||||||
|
Gross Requirements |
|
|
|
|
|
|
|
|
|
|
Scheduled Receipts |
|
|
|
|
|
|
|
|
|
|
Projected On Hand |
|
|
|
|
|
|
|
|
|
|
Net Requirements |
|
|
|
|
|
|
|
|
|
|
Planned-Order Receipts |
|
|
|
|
|
|
|
|
|
|
Planned-Order Releases |
|
|
|
|
|
|
|
|
|
|
Item: |
Lot Size: |
LT: |
SS: |
||||||
|
Gross Requirements |
|
|
|
|
|
|
|
|
|
|
Scheduled Receipts |
|
|
|
|
|
|
|
|
|
|
Projected On Hand |
|
|
|
|
|
|
|
|
|
|
Net Requirements |
|
|
|
|
|
|
|
|
|
|
Planned-Order Receipts |
|
|
|
|
|
|
|
|
|
|
Planned-Order Releases |
|
|
|
|
|
|
|
|
|
|
Horizon Period |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
Item: |
Lot Size: |
LT: |
SS: |
||||||
|
Gross Requirements |
|
|
|
|
|
|
|
|
|
|
Scheduled Receipts |
|
|
|
|
|
|
|
|
|
|
Projected On Hand |
|
|
|
|
|
|
|
|
|
|
Net Requirements |
|
|
|
|
|
|
|
|
|
|
Planned-Order Receipts |
|
|
|
|
|
|
|
|
|
|
Planned-Order Releases |
|
|
|
|
|
|
|
|
|
|
Item: |
Lot Size: |
LT: |
SS: |
||||||
|
Gross Requirements |
|
|
|
|
|
|
|
|
|
|
Scheduled Receipts |
|
|
|
|
|
|
|
|
|
|
Projected On Hand |
|
|
|
|
|
|
|
|
|
|
Net Requirements |
|
|
|
|
|
|
|
|
|
|
Planned-Order Receipts |
|
|
|
|
|
|
|
|
|
|
Planned-Order Releases |
|
|
|
|
|
|
|
|
|