This lab assignment gives you a chance to practice creating a WBS within your chosen PM software tool.
Requirements
Instructions
[NOTE: I am NOT asking you to work through the entire tutorial in Appendix B!!! The objective is for each student to show evidence of having selected, downloaded/installed (if necessary) a PM tool, and get your feet wet entering just the WBS into the tool. This is a very simple assignment and should take only a few minutes once you have selected and installed the PM software of your choice.] Please don’t over-think it.
• Submit your document to the instructor via Canvas as a .pdf file
Notes
Imagine that you are a project manager for a construction company. You must create a WBS for the Site Preparation phase of this project. Here is a list of tasks.
| Task | Title | Predecessors | Duration |
| A | Contract Approval | — | 5 |
| B | Site Survey | A | 5 |
| C | Permit Application | A | 4 |
| D | Grading | B,C | 5 |
| E | Sewer Lines | B | 7 |
| F | Base Paving | D | 3 |
| G | City Approval | C,F | 6 |
| H | Final Paving | E,G | 8 |