  • HW: Take off rebars and concrete

HW: Take off rebars and concrete

0 comments

Please look at the plans first! I need an Engineer tutor that have on screen take off or blue beam to take off plan. The answers going to be in excel spreadsheet. Please look at the requirments before you accept the this assinment. I’ll except a resonable offers. Thanks

Perform quantity take off for rebar and concrete between Lines 1-3 and A-C (Include entry at 1.5 & C)

Reinforcing (pounds)

1, Foundations

2, Slab

3. Masonry (up to the 2nd floor level)

Convert each to pounds per SF of building slab area

Concrete (CY)

1, Foundations

2, Slab

Convert each to CY per SF of building slab area

Show the resultant pounds of rebar per CY of Concrete

From your calculations, develop the total building quantities to be inserted into the structural tab of our spreadsheet. Identify the total quantity of reinforcing (LBS) and volume of concrete (CY) for the building slab/foundation.