Question 1: (4 Marks)

  • Draw the following network using Precedence Diagram Method and determine the critical path(s); PDMin; Total Float for each activity considering the following data:
ActivityDepends onDuration (days)
A6
B5
C6
DA5
EA,B8
FB3
GE6
HG8
IF9
JC,E7
KJ,H6

Question 2: (4 Marks)

ActivityDepends onDuration (days)
A3
B4
CA3
DA4
EB8
FA, B3
GB6
HD, G7
IF2
JH, I10

Question 3: (4 Marks)

The following table illustrates the activities of a small project:

ActivityDuration (Days)Depends On
A10
B3A & F
C7G
E5A & G
F11
G10J
H9 E & I & B
I4C
J6
K5B

It is required to:

  • Draw Activity On Node “AON” Network;
  • Calculate ES, EF, LS, LF for each activity;
  • Highlight and Write the Critical Path;
  • Find activity total float;
  • Find activity free float.

Question 4: (4 Marks)

ActivityDepend OnDuration
C6
A7
B8
DA & B9
GC6
EC5
HB & C7
FE & H10

Given a small project as shown in table:

It is required to:

  • Draw (PDM) network;
  • Calculate activity times;
  • Find project duration;
  • Locate critical path;
  • Find total float of each activity;
  • Find free float of each activity;
  • Convert to (ADM) network.

Question 5: (4 Marks)

Given a list of activities for a small project as shown in the following table:

ActivityDuration (days)Early StartEarly FinishLate StartLate FinishTotal FloatFree Float
A 05  0 
B 511  0 
C 1113  6 
D 04  1 
E 47  4 
F 1119  0 
G 1920  0 

It is required to:

  • Complete the missing data in the table; and
  • Draw The Activity-On-Node network, assuming that any relationship you need is FS=0.